第二层露天平台防水工程施工工艺,程序须知 1 原楼板填缝,各坑洼处抹平。(作用:节约防水材料) 2 地脚线位置,开凿凹进2cm。(柔性防水材料,必须用沙浆覆盖)
3 地面除灰尘,沙粒。 并且楼面须干燥一天。(增加防水的附着性)
4 采用有弹性的沥青油材料,滚涂仔细不留死角。(弹性须适应南非约翰内斯堡的昼夜巨大温差,不发生脆裂)
5 在沥青油防水层上,覆盖纤维布。
6 在纤维布上再重复滚涂沥青材料一次。(增加强度和防水性能)
7 覆盖塑料薄膜膜后。做7天闭水试验。不漏水,成功防漏后,进入下一步工序。(及时发现并整改,减少更大的损失)
8 膜上铺设钢丝网,轻拿轻放,保护好防水层。用沙浆做走水坡面面。保证有5cm落差。落水口为两110管。(不积水,雨水流走快速)
9 干燥后,在走水坡面上涂刚性聚合物防水剂。(防止砂浆层存水。注意:室内浴室防水只需此道工序) 10 铺设地砖,留0.5cm砖缝。用膨胀性水泥填缝。
The first floor open platform waterproof project construction proce, program instructions 1 original floor seam filling, each place certainly some pits.Function: save (waterproof material), 2 the anchor line position, digging 2cm instead.Flexible waterproofing materials, must (with mortar) 3 ground remove dust, sand.And the floors shall be dry.(the adhesion) increased waterproof 4 using elastic material, coating of asphalt oil not carefully.Johannesburg, South Africa (elastic must adapt to the huge difference does not occur embrittlement), 5 oil in asphalt waterproof, covering fiber cloth.6 in fiber cloth repeat roll asphalt material.(to increase the intensity and waterproof properties), 7 cover plastic membrane.Do 7 days shutting water test.Don\'t slack, leakproof, after the succeful entering the next procedure.Timely discovery and rectification, (reduction greater lo), 8 the laying of steel wire, membrane gently with good protection of waterproof.Do everything with mortar don slope.Ensure 5cm gap.Water mouth for two 110 tube.(don\'t run fast, rain water),