中国水电路桥工程有限公司宝兰客专甘肃段项目经理部一工区 桩基工程安全专项施工方案

目 录

一、编制依据················································································································································ 1

二、适用范围················································································································································ 1

三、编制原则················································································································································ 1

四、安全目标················································································································································ 1

五、工程概况················································································································································ 1

六、工程地质情况 ········································································································································ 3

七、钻机选择、施工 ···································································································································· 4

八、灌注桩施工安全操作规程 ····················································································································· 4

九、钻机操作、钻孔安全、文明措施 ········································································································· 4

十、施工安全保证措施 ································································································································ 7

中国水电路桥工程有限公司宝兰客专甘肃段项目经理部一工区 桩基工程安全专项施工方案

钻孔灌注桩专项安全施工方案

一、编制依据

⑴《中华人民共和国安全法》

⑵《铁路桥涵工程施工安全技术规程》(TB10303-2009) ⑶ 陕西宝鸡至甘肃兰州第10合同段施工图设计。 ⑷《铁路路基施工安全技术规程》 (TB1032-2009) ⑸《高速铁路设计规范》 (TB10621-2009)

⑹《高速铁路桥涵工程施工质量验收标准》 (TB10752-2010) ⑺《高铁工程施工安全技术规程》 (TB10303-2009)

二、适用范围

陕西宝鸡至甘肃兰州第10合同段项目经理部一工区彭家咀中桥、王家岔大桥、郑家川大桥、蛟龙大桥、华尖川特大桥的全部桩基工程。

三、编制原则

1、安全第一的原则

在安全方案编制中始终按照技术可靠、措施得力、施工顺序合理、确保安全的原则确定施工方案。

2、坚持规范、规程原则

贯彻执行铁路路基施工技术规程、铁路工程安全施工技术规程。执行业主针对本工程建设制定的各项安全管理办法、细则和规程。施工时按照设计方案进行施工。

四、安全目标

1、杜绝死亡。

2、不发生高处坠物伤人事故。

3、不发生施工人员高处坠落

4、杜绝因施工造成的道路中段、管道、通信、电力管线损坏等施工责任事故。

五、工程概况

1 中国水电路桥工程有限公司宝兰客专甘肃段项目经理部一工区 桩基工程安全专项施工方案

根据设计图纸,桥梁结构形式及桥位处工程地质情况如下:

彭家咀中桥,桥梁全长84.70m,本桥上部采用3-24m简支箱梁,下部结构桥台为钻孔灌注桩基础、双线矩形空心桥台、圆端形实体桥墩、盖梁。地质该处土层主要为第四系全新统冲击风砂粘质黄土、粘质黄土、细圆砾土、第四系上更新统风积砂质黄土,基底为上第三系泥岩。。

王家岔大桥,桥梁全长128.10m,本桥上部采用1-32m+2-24m+1-32m的简支箱梁,下部结构采用钻孔灌注桩基础、双线矩形空心桥台、圆端形实体桥墩、盖梁。地质该处土层主要为第四系上更新统风积砂质黄土、冲积的砂质黄土及粘质黄土,沟底出露为上第三系泥岩。

郑家川大桥,桥梁全长144.10m,本桥上部采用4-32m简支箱梁,下部结构采用钻孔灌注桩基础、双线矩形空心桥台、圆端形实体桥墩、盖梁。地质该处土层主要为第四系全新统冲击砂质黄土、粘质黄土、细圆砾土、第四系上更新统风积砂质黄土及上第三系泥岩。

蛟龙大桥,桥梁全长144.10m,本桥上部采用4-32m箱梁,下部结构采用钻孔灌注桩基础、双线矩形空心桥台、圆端形实体桥墩、盖梁。地质该处土层为第四系上更新统冲积砂质黄土、粘质黄土,沟底出露为上第三系泥岩。

华尖川特大桥,桥梁全长4578.92m。本桥上部采用51孔32m+1孔24m+73孔32m+3孔24m+6孔32m+1孔24m+1孔32m+1孔24m+4孔32m简支箱梁。下部结构采用钻孔灌注桩基础,双线矩形空心桥台,圆端形空心桥墩、盖梁。地质该处地层主要为第四系全新统冲积砂质黄土、粘质黄土、粉土、中砂、砾砂、细圆砾土,基地为上为第三系泥岩。

桩基全部采用钻孔灌注桩施工。

2 中国水电路桥工程有限公司宝兰客专甘肃段项目经理部一工区 桩基工程安全专项施工方案

六、工程地质情况

1、地形、地貌

彭家咀中桥位于定西市安定区彭家咀,DK910+280C处有一冲沟,土质沟床沟型较顺直,沟内植被良好,季节性流水。

王家岔大桥位于定西市安定区宁远镇,地貌上属黄土梁沟壑区,地形起伏较大,地面高程1980-2030m最大相对高差为50m。

郑家川大桥位于定西市安定区彭家咀,地貌上属于牛谷河南岸黄土梁沟壑区,地势平坦。

蛟龙大桥位于定西市安定区宁远镇蛟龙村附近,地貌上属于黄土梁沟壑区。

华尖川特大桥位于东河河谷阶地区,地形平缓,地面高程1951-1972m最大相对高差约为20m。岸坡坡度不大,岸坡稳定。

2、气象、水文

根据设计图纸提供的水文气象资料可知,项目区属于典型的中温带大陆性气候,总的气候特点是:冬季漫长而寒冷,项目夏季炎热而短促,春秋气温变化剧烈。全年降雨少而集中,多集中在

7、8两个月,降雨年际变化大,最低年份仅为143.5mm,最高年份为635.5mm,年平均417.5mm,蒸发量年平均为2093mm。每年一月最冷,平均最低气温-19℃,极端最低温度为-34.5℃;极端最高气温为37.5℃,无霜期约118-152天,初霜日平均为9月30日,终日为5月7日。最大风速24.5m/s,最大积雪厚度12cm,年平均相对湿度55﹪。

3、工程地质

主要以山前冲洪积平原为主,河流冲积平原为辅,岩土类型较为稳定,工程地质条件较好。

区内地下水较丰富,主要为第四系松散层空隙潜水和基岩裂隙水,地下水位在丘陵顶部埋藏较深,而河谷附近则埋藏较浅。平均流量1.1亿立

3 中国水电路桥工程有限公司宝兰客专甘肃段项目经理部一工区 桩基工程安全专项施工方案

方米,最大流量2840立方米∕秒。

七、钻机选择、施工

本工程钻孔选用YTR220型钻孔机6台,按拟定的施工顺序分段开始施工,主桥按单独工期体系进行安排施工。钻机安装就位严格按照《建筑机械使用安全技术规程》(JGJ33-2001)操作规程施工,钻机安装就位后用水平尺使底座保持水平,钻杆上下垂直。

八、灌注桩施工安全操作规程

1、电器设备要设置漏电开关,并保证接地有效可靠。

2、登高检修与保养的操作人员,必须穿软底鞋,并将鞋底淤泥清除干净。

3、作业区要严加安全管理,任何人不准进入,主钢丝绳要经常检查,三股中发现断丝数大于 10丝时,应立即更换。

4、使用钻杆作业时,要经常检查限位结构,严防脱落伤人或落入孔洞中;检查时避免用手指伸入探摸,严防轧伤。

5、钻杆与钻头的连接要勤检查,防止松动脱落伤人。

6、采用泥浆护壁时,对泥浆循环系统要认真管理,及时清扫场地上的浆液,做好现场防滑工作。

7、钻孔后,混凝土浇灌顶标高比地面低时,应在孔口加盖板封挡,以免人或工具掉落孔中。

8、吊置钢筋笼时,要合理选择捆绑吊点,并应拉好尾绳,保证平稳起吊,准确入孔,严防伤人。

九、钻机操作、钻孔安全、文明措施

1、安装钻孔机前,应掌握勘探资料,并确认地质条件符合该钻机的要求,

4 中国水电路桥工程有限公司宝兰客专甘肃段项目经理部一工区 桩基工程安全专项施工方案

地下无埋设物,作业范围内无障碍物,施工现场与架空输电线路的安全距离符合规定。

2、安装钻孔机时,钻机钻架基础应夯实、平整。钻架下应铺设枕木。

3、钻机的安装和钻头的组装应按说明书规定进行,竖立或放倒钻架时,应有熟练的专业人员进行。

4、钻架的吊重中心、钻机的卡孔和护进管中心应在同一垂直线上,钻杆中心允许偏差为20㎜。

5、钻头和钻杆连接螺纹应良好,滑扣时不得使用。钻头焊接应牢固,不得有裂纹。钻杆连接处应加便于拆卸的垫圈。

6、施工区域设置警戒线,有专人负责看护。

7、作业前重点检查项目应符合下列要求:

1)各部件安装紧固,转动部位和传动带有防护罩,钢丝绳完好,离合器、制动带功能良好。

2)润滑油符合规定,各管路接头密封良好,无漏油、漏气、漏水现象。

3)电气设备齐全、电路配置完好。

4)钻机作业范围内无障碍物。

8、作业前,应将各部操纵手柄先置于空档位置,确认一切正常后,方可作业。

9、开机时,应先送浆后开钻;停机时,应先停钻后停浆。泥浆泵应有专人看管,对泥浆质量和浆面高度应随时测量和调整,保证泥浆浓度合适。停钻时,出现漏浆应及时补充。并应随时清除沉淀池中杂物,保持泥浆纯净和循环不中断,防止塌孔和埋钻。

5 中国水电路桥工程有限公司宝兰客专甘肃段项目经理部一工区 桩基工程安全专项施工方案

10、开钻时,钻压应轻,钻速应慢。在钻进过程中,应根据地质情况和钻进深度,选择合适的钻压和钻速,均匀给进。

11、变速箱换档时,应先停机,挂上档后再开机。

12、加接钻杆时,应使用特制的连接螺栓均匀紧固,保证连接处的密封性,并做好连接处的清洁工作。

13、钻进中,应随时观察钻机的运转情况,当发生异响、吊索具破损、漏气、漏渣,以及其它不正常情况时,应立即停机检查,排除故障后,方可继续开钻。

14、提钻、下钻时,应轻提轻放。钻机下和井孔周围2米以内及高压胶管下,不得站人。严禁钻杆在旋转时提升。

15、发生提钻受阻时,应先设法使钻具活动后再慢慢提升,不得强行提升。如钻进受阻时,应采用缓冲击法解除,并查明原因,采取措施后,方可钻进。

16、钻架、钻台平车、封口平车等的承载部位不得超载。

17、使用空气反循环时,其喷浆口应遮拦,并应固定管端。

18、钻进进尺达到要求时,应根据钻杆长度换算孔底标高,确认无误后,再把钻头略为提起,降低转速,空转5—20min后再停钻。

19、钻机的移位和拆卸,应按照说明书规定进行,在转移和拆运过程中,应防止碰撞机架。

20、作业后,应对钻机进行清洗和润滑,并应将主要部位遮盖妥当。

21、严格按照文明卫生施工要求,提高职工素质,确保工程完成。作业时,禁止直接或间接向河道排放泥浆,禁止泥浆外泄污染环境,泥浆池周边

6 中国水电路桥工程有限公司宝兰客专甘肃段项目经理部一工区 桩基工程安全专项施工方案

设置醒目安全警示标牌,并用安全网围护,防止小孩入内观望。

22、未及时灌注的桩孔及护筒需用安全平网严实遮盖,防止路人误撞入,每台钻机上设置醒目安全警示标牌,时刻警示操作人员及他人。

十、施工安全保证措施

(一)、施工中的安全措施

1、施工人员必须戴安全帽,穿绝缘胶鞋,孔周边作业人、监护人员,必须戴安全帽,严禁穿拖鞋、赤脚、酒后上岗作业。

2、施工现场电源线路,必须按“三级配电”“二级漏电分级”分段保护。

3、各孔井用电必须分闸,严禁一闸多孔和一闸多用。必须一机一闸一漏一箱进行敷设。

4、孔上电线、电缆必须架空。

5、电箱一律采用铁质电箱,电箱应有严密的防雨措施,安装位置合适,安装牢固,进出线整齐,拉线牢固,熔丝不得用金属代替,箱内不得放其它物品。

6、现场电源线路及电气设备,由持证电工负责安装维护,经验收合格后,方准投入使用。

7、施工现场所有设备和机具必须做好保护接零。

8、所有机械设备的传动部位,必须装设防护罩。

9、垂直起重设备必须经常性检修维护,保证机件能够运转正常,操作灵活,按钮开关、减速器、钢丝绳、绳卡、吊钩、吊桶、吊笼等,不得带病作业。

7 中国水电路桥工程有限公司宝兰客专甘肃段项目经理部一工区 桩基工程安全专项施工方案

10、垂直起重设备支架应牢固,应能承受一定的冲击力不至翻倒,垂直起重设备必须经检验合格后,方可投入使用。

(二)、施工现场安全防护措施

1、夜间施工时,要有足够的照明,施工危险区域,白天悬挂明显标志,夜间悬挂标志灯。

2、事故易发部位,如本工程高空作业处,起吊区,用电机械等安排专职的安全员进行指挥与监督;

3、现场施工特种作业人员要佩带专门的防护用品,如电焊工要佩带护目镜和面罩,高空作业系好安全带。

4、所有现场施工人员严禁酒后上岗。

5、现场施工道路的交叉处或拐弯处设立安全警告标志。

6、变压器周围设高度不低于1.7米的安全护栏,四周挂上“小心!高压危险”的警告牌。

7、定期进行安全生产检查工作,对检查出的不安全因素和隐患应立即整改,整改不力的悬挂警告黄牌,直至整改完毕。

8、工地入口处设安全告示板,宣传施工安全信息,安全检查记录,整改情况。

9、办公室加强与气象部门联系,重点收集高温、洪水等方面的资料,一旦发现有危及工程安全及人员安全的灾害气象预兆时,立即上报项目领导,及时采取措施。

(三)、突发事件发生时的处理应急方案

1、应急救援处置预案机构

8 中国水电路桥工程有限公司宝兰客专甘肃段项目经理部一工区 桩基工程安全专项施工方案

1) 工区应急救援处置预案指挥机构为安全生产领导小组。在应急抢险队人员、通讯、交通车辆、物资器材、工具、资金等方面实施抢险救援中起绝对保证作用,满足抢险救援。其应急抢险救援领导小组成员如下: 组 长:李传州

副 组 长:孙尔林 赵春寿 王京龙 高先峰 张兆奎 汪叶滨 组 员: 王亮 张宏 刘永胜 李双平王志明

2、几种意外事故的应急救援程序

1)雪灾灾害事故。班组、作业队要立即报告项目部,项目部再视灾害程度组织应急队抢救的决定。作业队要立即组织人员抢险,保护员工,减少财产损失。

2)发生地震灾害事故,基层作业队要立即组织员工疏散,同时立即报告项目部,项目部下令调派应急队赶赴现场进行救援抢险。

3)发生消防火灾事故。一旦发生火灾险情,早发现早扑灭采取果断措施扑灭火灾和防止火势蔓延,疏散人员,抢救财产,并立即报告项目部,项目部再视情况报告消防部门和当地政府、林业部门呼救“119”支援抢险。

4)发生爆炸事故。一旦发生爆炸事故,项目部安全生产领导小组立即组织抢险队员抢险,并拨打“110”报警电话,请求地方公安部门支援。

5)发生雷电灾害事故。一旦遇暴风骤雨天气有雷电情况发生,工人要立即暂停施工,回棚(房)躲避,并远离大树下、铁吊架下等,撑伞不能紧握金属支撑杆。当雷雨现象比较严重时,要立即切断动力电源,并且关掉一切用电器。尽量少使用手机等无线射频设备。

6)停水、停电事故。起用储备用水,根据停水时间合理供应水;起用发电

9 中国水电路桥工程有限公司宝兰客专甘肃段项目经理部一工区 桩基工程安全专项施工方案

机,保证重要设备、施工供电;将外部供电线路总闸断开,接到供电通知后再使用外部供电。

7)有毒有害气体油料泄露事故。接到泄露报告后,项目部安全生产领导小组立即组织人员抢修,抢修人员必须佩戴防毒面具,收集或稀释泄露物质。

8)中毒、急性传染病事故。项目部安全生产领导小组立即组织专业人员进行抢救,安排车辆将病员以尽快速度送往医院,或者拨打“120”请求支援。

9)设备大修、故障事故。主管部门立即联系租用或起用备用设备,组织人员抢修设备。

3、施工常见事故的应急救援程序

1)发生轻伤事故后,首先抢救伤员,事故现场有关人员要立即报告,采取措施防止事故的扩大。轻伤事故由班组、作业队组织有关人员调查处理,作业队登记,报项目部存查。项目部、作业队按《安全生产管理办法》有关规定处罚

2)发生重伤、死亡事故,事故现场有关人员要立即报作业队和项目部,同时立即抢救伤员保护现场。作业队和项目部在收到事故报告后,立即组织工会、技术、安全部门等组成事故调查组,立即赶赴现场调查了解,分析事故原因,在24小时内报当地劳动安全监督管理局和检察院,由当地县(市)一级政府调查处理批复结案,然后项目部再按《安全生产管理办法》有关规定进行处罚处分。

3)发生交通事故,首先当事者立即抢救伤员、保护现场,立即报告当地公安交警部门赶赴现场调查处理,同时立即报告作业队和项目部

钻孔灌注桩施工专项安全方案

钻孔灌注桩冬季施工方案

钻孔灌注桩施工方案(冲击钻)

钻孔灌注桩基础施工方案

钻孔灌注桩施工常见问题

钻孔灌注桩施工合同

首件钻孔灌注桩施工方案

钻孔桩安全专项施工方案

钻孔灌注桩施工安全技术保证措施

钻孔灌注桩施工质量通病专项治理总结

钻孔灌注桩施工专项安全方案
《钻孔灌注桩施工专项安全方案.doc》
将本文的Word文档下载到电脑,方便编辑。
推荐度:
点击下载文档
点击下载本文文档